Map Location and list of 35 Towns situated on the bank of River Ganga, River Ram Ganga and River Kali in the Ganga Basin in U.P
Projects
S.No. Name Description Date (Sanctioned & Scheduled date of completion) Progress upto January-2017
Physical Financial(in Crores)
1 Sewerage and non-sewerage Schemes for Pollution Abatement of River Ganga at Allahabad U.P. Construction of 4 Nos. STP Total Capacity 105 MLD, Laying of 14.4 Km Sewer Line, 143 Nos. Community Toilets and 5 Nos. Dhobi Ghat etc. in Allahabad Town. Total Cost of Project 305.34 Crore. Sanctioned by GOI on 06/05/2010 and Scheduled date of completion is February,2013 100% 255.37
2 Sewerage Works in Sewerage District-E of Allahabad U.P. Construction of 2 Nos. Sewage Pumping Station and laying of 109.2 Km Sewer Line in Sulemsarai area of Allahabad Town. Sanctioned by GOI on 22.02.2011 and scheduled date of completion is February,2013 Sanctioned cost 142.00 100% 129.74
3 Sewerage Works in Sewerage District-C of Allahabad U.P Sewer Work 134 Km S.P.S.-1 No. Lift Station 1 No. Sanctioned cost 146.87 38% 35.12
4 14 MLD Salori STP at Allahabad. S.T.P.14 MLD S.P.S 2 No. Rising Main 170 Meter Sanctioned cost 42.40 100% 19.73
5 Sewerage Works in Sewerage District-A of Allahabad U.P. Sewer Network 242 KM S.P.S 3 Nos. Rising Main 2.335 KM Sanctioned cost 288.94 25% 58.61